As you may know, LADWP is planning construction to add more circuits that will increase electric capacity in the greater Bel Air area. The intention of this upgrade is to improve reliability in the Bel Air, Beverly Crest, Westwood, and Holmby Hills neighborhoods. Construction on Sunset Blvd will begin Tuesday June 18, 2019 at 9:00am.
Please note:
- Construction hours are Monday through Friday 9:00 am to 3:30pm and Saturday 8:00am through 6:00pm.
- You can expect to see crews working primarily in the middle two lanes on Sunset Blvd.
- During construction, at least one lane will be open in each direction to maintain both eastbound and westbound traffic flow.
- At the end of each work day, all lanes will be reopened to traffic.
- Crews will be working simultaneously at the following locations:
1) Sunset between the 405 Freeway and Bellagio Rd. Crews will begin work near the 405, working about 500 feet at a time and progressing eastward toward Bellagio Rd.
2) Sunset between S. Beverly Glen Blvd. and Carolwood Dr.
Attached please find a fact sheet. The project website is currently under development; it will be shared as soon as it is available.